Switching to the future in Nordermeldorf too

Share this news

What makes an ordinary construction site job extraordinary.

Sustainability is an investment in the future: SCHEIDT offers the right solution for security of supply and the energy transition with its stations, substations and structures. SCHEIDT expertise was therefore in demand for the construction of wind turbines in the municipality of Nordermeldorf, between Heide in the north-east and Meldorf in the south-east and Büsum in the west. Let's accompany TEAM SCHEIDT as they work on the construction site on behalf of Actemium Deutschland, a strong partner in the advancement of technology.

Dietmar Grosser, an assembly manager with many years of experience at SCHEIDT, is responsible for the project. He is in charge of everything in this project with numerous walk-in stations in element construction. In Nordermeldorf, the construction site was looking forward to 2 BEK: 1 x BEK 330-630 and 1 x BEK 330-630, which were joined together at the front as a building combination with complete electrical fittings already in the factory, with thermal insulation façade and sandwich roof.

Site inspection 4 weeks before the installation date for the transformer stations.
Together with the customer, the construction site was visited in good time in order to check many things on site, e.g: Where can the extra-wide lorries drive in and park? Where is the best place for the crane, etc.? In Nordermeldorf, up to 42 tonnes had to be carried at a distance of 18 m! No problem for TEAM SCHEIDT, of course. The order in which the stations are set up is determined on the basis of the inspection.

Unique solutions, impressively flexible.
A lot is changing in terms of technology as a result of e-mobility - SCHEIDT is well positioned and offers the latest technologies for electrical engineering. The types of transformer stations are also subject to constant change. It's a good thing that SCHEIDT offers a 6-fold larger model range thanks to the 10 cm model grid. This meant that the two BEKs could be supplied to match. For a clean, safe and economical energy supply, so that the world remains liveable for future generations. It is no coincidence that the company plays in the premier league in the station market and will make the decisive difference for many more energy transition projects.

TEAM SCHEIDT at work in Nordermeldorf

Big things on the hook: the individual transformer stations are placed in their intended position using a heavy-duty crane. An important milestone as a progressive contribution to the energy transition.

The truck really has a load to carry here: up to 42 tonnes have to be transported and moved. SCHEIDT specialists are there every step of the way to ensure that everything runs smoothly.

It is the human element that counts and leads to top performance in the team. SCHEIDT lives this claim like no other for a perfect result and maximum customer satisfaction.

Related news

Scheidt at the career information day in Stadthagen

Review of the career information day in Stadthagen - Training at Scheidt

Last week we were together with 92 other ...

read more →

The concrete whisperer from Rinteln - an article in the Schaumburger Zeitung

The concrete whisperer from Rinteln - an article in the Schaumburger Zeitung

We are delighted about the exciting article in the Schaumburger ...

read more →

Test report and cover letter from 1970

Safety with tradition - the history of arc fault testing

When were the first arc fault tests carried out? The Scheidt company can ...

read more →

View all news
en_GB